Asbestos Removed From Melbourne Tram Sub-Stations

Melbourne has had its fair share of asbestos tragedies in the past, but this substance that is controversial has managed to creep it back in the construction sector through inferior quality control in vetting and material selection of providers.

There are four new electric substations with asbestos flooring. Yarra Trams ran to procure the four sites after testing found that there’s a tiny risk of exposure to the harmful material.

This past year, three modular electrical substations were built in the CBD, East Brighton, and Thornbury. There is one which is still under construction in West Brunswick. Each one of these substations has white asbestos flooring prohibited in Australia in the year 2003.

In mid-September, Yarra Trams was told about the illegal existence of asbestos. Siemens subsequently subcontracted the work based Robin Johnson Engineering.

Asbestos Removed From Melbourne Tram Sub-Stations

Chinese Company Deceived Australian Engineering Firm
Last month, it had been found out that Robin Johnson Engineering used asbestos materials in 2 new electric substations. This is an emerging tendency which has made Eradication state and Australia’s Asbestos Safety that this was just the tip of the iceberg.

Robin Johnson who’s the firm’s managing director said that Siemens and Yarra Trams were notified as soon as the asbestos was found.

He likewise stated that the Chinese supplier had misled his firm. Nevertheless, he refused to give the name of the Chinese supplier.

The South Australian company has asserted that they had been deceived by the Chinese supplier by supplying documentation that the flooring material they delivered was free.

Yarra Trams testing found that asbestos was present in 7 out of the 24 swab samples from substations Elizabeth Street in Brighton East the town, and Thornbury. Nevertheless, it returned a negative atmosphere sample.

Thornbury residents complained that the substation built had taken a sizeable ball of a small local park along with a children’s playground up.

On Monday, contractors who are certified for asbestos testing Melbourne commenced the safe disposal of the materials wearing full protective equipment and following safe procedures.

Phil Altieri who’s the tram department secretary of the Rail, Tram, and also the Bus Union said it was incredibly disappointing to discover that asbestos was installed even after there was a major plan to remove it from your tram network in the 1990s.

Simon Murphy, the spokesman or Yarra Trams stated the company had the websites scrutinized by independent experts who concluded that the risk of exposure to individuals who enter the site and also the general public is insignificant.